Question: #1) Data for a project is given below . NOTE : The project started on February 1st and is (currently) at the end of June.

#1) Data for a project is given below.

#1) Data for a project is given below . NOTE :

NOTE:

  1. The project started on February 1st and is (currently) at the end of June.
  2. The project has a planned duration of 6 months.
  3. The table below provides Planned Cost (in thousands) for each activity (A through G) for the months of February through July.
  4. The table below provides Actual Cost (in thousands) incurred for the months of February through June.
  5. Use percent completion rule in your calculations.

#1) Data for a project is given below . NOTE :

  1. Compute Critical Ratio for the project. What can be done to improve Critical ratio for the project? Explain. (6 points)
  2. Based on current cost performance level, what is the expected cost savings in completing the project? (3 points)
  3. Based on current schedule performance level, how much more time (in months) is needed to complete the project? (3 points)

(Months) Activity Duration 2.00 1.00 2.00 mowo Budget OR Plnd. Cost (thousands 15.00 5.00 10.00 21.00 32.00 5.00 5.00 % Completed 1.00 1.00 1.00 0.50 0.50 0.50 0.50 3.00 2.00 1.00 1.00 Act. March Apr May Jun Jul 7.50 Duration Feb (Months) 2.00 | 7.50 1.00 2.00 3.00 2.00 1.00 1.00 13.00 5.00 5.00 7.00 5.00 7.00 16.00 7.00 16.00 5.00 5.00 15.00 Actual Cost (AC) 13.00 14.00 9.00

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!