Question: 1. Data for a project is given below . (Months) Budget OR Activity Duration Plnd. Cost (thousands) % Completed A 2.00 15.00 1.00 B 1.00
1. Data for a project is given below.
| (Months) | Budget OR | |||
| Activity | Duration | Plnd. Cost (thousands) | % Completed | |
| A | 2.00 | 15.00 | 1.00 | |
| B | 1.00 | 5.00 | 1.00 | |
| C | 2.00 | 10.00 | 1.00 | |
| D | 3.00 | 21.00 | 0.50 | |
| E | 2.00 | 32.00 | 0.50 | |
| F | 1.00 | 5.00 | 0.50 | |
| G | 1.00 | 5.00 | 0.50 |
NOTE:
- The project started on February 1st and is (currently) at the end of June.
- The project has a planned duration of 6 months.
- The table below provides Planned Cost (in thousands) for each activity (A through G) for the months of February through July.
- The table below provides Actual Cost (in thousands) incurred for the months of February through June.
- Use percent completion rule in your calculations.
|
|
|
|
|
|
|
| ||||||||||
| Act. | Duration (Months) | Feb | March | Apr | May | Jun | Jul |
|
|
| ||||||
| A | 2.00 | 7.50 | 7.50 |
|
|
|
|
|
|
| ||||||
| B | 1.00 |
|
| 5.00 |
|
|
|
|
|
| ||||||
| C | 2.00 |
|
| 5.00 | 5.00 |
|
|
|
|
| ||||||
| D | 3.00 |
|
| 7.00 | 7.00 | 7.00 |
|
|
|
| ||||||
| E | 2.00 |
|
|
|
| 16.00 | 16.00 |
|
|
| ||||||
| F | 1.00 |
|
|
|
| 5.00 |
|
|
|
| ||||||
| G | 1.00 |
|
|
|
| 5.00 |
|
|
|
| ||||||
| Actual Cost (AC) | 13.00 | 13.00 | 14.00 | 9.00 | 15.00 |
|
|
|
| |||||||
- Compute Critical Ratio for the project. What can be done to improve Critical ratio for the project? Explain.
- Based on current cost performance level, what is the expected cost savings in completing the project?
- Based on current schedule performance level, how much more time (in months) is needed to complete the project?