Question: 1. Data for a simplified PERT network are given below: i 5 5 10 10 15 15 20 25 30 30 35 40 10
1. Data for a simplified PERT network are given below: i 5 5 10 10 15 15 20 25 30 30 35 40 10 j 10 15 20 25 25 30 35 35 35 40 45 45 ACT A B C E dl 20 F G L d2 M N P 30 Time Estimates (days) a 7 2 5 8 0 M 7 4 3 0 4 3 5 m 10 5 7 10 0 10 6 5 0 7 6 6 35 40 b 16 N P 6 11 11 11 7 11 0 9 11 7 45 a. After calculating the mean and standard deviation for each activity duration, calculate Early Event Times (TE) and Late Event Times (TL) for all nodes. b. Determine the PERT "critical path(s)" and the mean and standard deviation for the project duration. Determine the probability of completing the project in 31 days or less. d. Determine the probability of completing the project in 33 days or more. e. Determine the probability of reaching event/node 35 in 24 days or less.
Step by Step Solution
3.53 Rating (150 Votes )
There are 3 Steps involved in it
a To calculate the Early Event Times TE and Late Event Times TL for all nodes we first need to calcu... View full answer
Get step-by-step solutions from verified subject matter experts
