Question: 1) Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $ 6,400 ACWP = $ 7,800 Project duration = 40 days Data date:
1) Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $ 6,400 ACWP = $ 7,800 Project duration = 40 days Data date: 10 days
1.1) Perform the following analyses of the project based on the data given above. a. Cost Variance b. Schedule Variance
1.2) Plot an S-Curve and show CV and SV on it. professional quality work
1.3) Interpret results to explain the project status
2)Explain the purpose of a Control Chart being as detailed as possible with words and use illustrations as well to explained it better
3)Please explain why large initial separations on the EV S-Curve between the lines for ACWP and BCWP with BCWP above the ACWP may be an indicator of excessive front loading. Use detailed words and explanations and illustrations to explain it
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
