Question: Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $ 6,400 ACWP = $ 7,800 Project duration = 40 days Data date: 10

Data: Total budget = $25,000 BCWS = $ 8,333 BCWP = $ 6,400 ACWP = $ 7,800 Project duration = 40 days Data date: 10 days 1) Perform the following analyses of the project based on the data given above. a. Cost Variance (5 points) b. Schedule Variance (5 points) 2) Plot an S-Curve and show CV and SV on it. (30 points). Please submit only professional quality work to receive full credit. All rough sketches and unclear submissions will receive partial credit or be returned ungraded. 3) Interpret results to explain the project status (10 points)