Question: 1 . Determine the pathsfor completion of this project, their durations, and the critical path. ( 5 pts ) Paths show letters for tasks Durations

1. Determine the pathsfor completion of this project, their durations, and the critical path. (5 pts)
Paths show letters for tasks Durations show individual #s
Total Duration (* next
to Critical Path)
2. If GETTING THE ELECTRIC INSPECTED (Task D) is delayed by 3 days, what is the resulting impact to the project (if
any) and why this happened (there is one very specific reason).(2 pts)
Answer: The resulting impact is:
Reason: Thisis because:
3. Assume the delay is eliminated (and you are back to the original results from Q1). If Wes and Steve want to
shorten the project by 3 days and have a budget of $3,000 to do so, will it be possible? You mustshow activities
crashed, total crash cost and proof using a crash diagram as taught in class lectures. (18 pts)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!