Question: 1. Develop a gantt chart and a pert diagram. 2. Answer the following questions: - List all the paths. - Compute for the length of

1. Develop a gantt chart and a pert diagram.

2. Answer the following questions:

- List all the paths.

- Compute for the length of each path.

- Determine the critical path.

- Figure out the shortest time to complete the project.

1. Develop a gantt chart and a pert diagram. 2.

ACTIVITY PREDECESSOR DURATION None 2 B 6 A 3 D B 4 E 2 F D 3 G D, E 2 H 3 1 F, G 2