Question: 1 . Develop a network diagram ( AKA precedence diagram ) . 2 . Calculate the expected duration for each activity. Determine the ES ,

1. Develop a network diagram (AKA precedence diagram).
2. Calculate the expected duration for each activity. Determine the ES, EF, LS LF, and slack for each activity.
3. Using your calculations determine the critical path and highlight it on your diagram.
4. Calculate the variance and standard deviation of the project's total duration. What is the probability that the project will be finished within 270 days (that is 270 days or less)?