Question: Using the schedule information given below, draw an AON network diagram showing activity Lesend durations. Use the legend below. Calculate ES , EF , LS

Using the schedule information given below, draw an AON network diagram showing activity
Lesend
durations. Use the legend below.
Calculate ES, EF, LS, LF, TF, and FF for each activity. Fill the following table with
ES, EF, LS, LF, TF, and FF values for the corresponding activity. Put Y in the last
(critical) column if the activity is critical. Place integers only for ES, EF, LS, LF, TF,
and FF.
What activity(ies) has the largest total float in days? List all.
What activity has the largest free float in days?
The largest free float is
day?
What if activity E took extra 4 days, what would happen? Select ALL correct answers.
A. The new project duration will be 25 days.
B. The critical path will change.
C. The new project duration will be 27 days.
D. The critical path will be the same
What if activity D took extra 3 days, what would happen? Select AL. correct answers.
A. The critical path will change.
B. The project will be delayed by 1 day.
C. The critical path will be the same.
D. The project duration will be the same.
What if activity C took extra 3 days, what would happen? Select ALL correct answers.
A. The critical path will change.
B. The new project duration will be 27 days.
C. The new project duration will be 25 days.
D. The project will keep the same critical path.
 Using the schedule information given below, draw an AON network diagram

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!