Question: Using the schedule information given below, draw an AON network diagram showing activity Lesend durations. Use the legend below. Calculate ES , EF , LS
Using the schedule information given below, draw an AON network diagram showing activity
Lesend
durations. Use the legend below.
Calculate ES EF LS LF TF and FF for each activity. Fill the following table with
ES EF LS LF TF and FF values for the corresponding activity. Put Y in the last
critical column if the activity is critical. Place integers only for ES EF LS LF TF
and
What activityies has the largest total float in days? List all.
What activity has the largest free float in days?
The largest free float is
day?
What if activity E took extra days, what would happen? Select ALL correct answers.
A The new project duration will be days.
B The critical path will change.
C The new project duration will be days.
D The critical path will be the same
What if activity D took extra days, what would happen? Select AL correct answers.
A The critical path will change.
B The project will be delayed by day.
C The critical path will be the same.
D The project duration will be the same.
What if activity C took extra days, what would happen? Select ALL correct answers.
A The critical path will change.
B The new project duration will be days.
C The new project duration will be days.
D The project will keep the same critical path.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock