Question: 1. Develop a network diagram for the project and identify the critical path and its duration in weeks. 2. Taking the critical path duration into

1. Develop a network diagram for the project and identify the critical path and its duration in weeks.
2. Taking the critical path duration into consideration, the client has asked to reduce the schedule by 6 weeks. How can we achieve this reduction without reducing the activity durations.
Note: Activity 1.1 cam be ignored while network diagram creation.
1.0 City Sports Complex 1.1 Design, Project Management & Control 1.2 Site Preparation 1.3 Civil Works 14 Building 1.5 Building Equipment 1.6 Finishing 1.7 Inspection & Handover 1.2.1 Hazardous Waste 1.3.1 Excavation 1.4.1 External Structure 1.5.1 Heating & Ventilation Equipment 1.6.1 Ice Hockey Arena 1.7.1 Final Inspection & Testing 1.2.2 Garbage / Other Waste Removal 1.3.2 Foundation 1.4.2 Roof 1.5.2 Refrigeration Equipment 1.6.2 Multi-Purpose Gym 1.7.2 Handover & Training 1.2.3 City Utility Connections 1.4.3 Interior Structure 1.5.3 Electrical Switchboard 1.6.3 Running Track 1.5.4 Water and Plumbing Equipment 1.6.4 Changerooms and Washroons 1.5.5 Fire Water Equipment 1.6.5 Daycare CentreStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts