Question: A project comprises the activities shown in the table, which also shows the duration of the activities. Activity A Preceding activity Duration (hours) 4

A project comprises the activities shown in the table, which also shows

A project comprises the activities shown in the table, which also shows the duration of the activities. Activity A Preceding activity Duration (hours) 4 B 9 C A, B 15 D C 3 E C 13 F D 3 G F 6 H E 16 (a) Construct the network diagram for the project. (b) Identify the critical path. (c) Calculate the expected completion time for the project. D. (b) The critical path from the project is F H