Question: 1. Develop a network drawing for Towns Construction and determine the critical path. How long is the project expected to take? 2. What is the
1. Develop a network drawing for Towns Construction and determine the critical path. How long is the project expected to take?
2. What is the probabilityof finishing in 270 days?
Minnesota State University Project Data
Activity | Description | Predecessor(s) | Optimistic | Likely | Pessimistic | Cost/Day |
A | Bonding, insurance, tax structuring | 21 | 24 | 45 | $1,500 | |
B | Foundation, concrete footings for boxes | A | 20 | 60 | 70 | $3,500 |
C | Upgrading skybox stadium seating | A | 50 | 60 | 100 | $4,000 |
D | Upgrading walkways, stairwells, elevators | C | 36 | 50 | 100 | $1,900 |
E | Interior wiring, lathes | B | 35 | 40 | 45 | $9,500 |
F | Inspection approvals | E | 1 | 1.5 | 2 | 0 |
G | Plumbing | D, F | 22 | 26 | 36 | $2,500 |
H | Painting | G | 15 | 25 | 35 | $2,000 |
I | Hardware/AC/metal workings | H | 20 | 25 | 60 | $2,000 |
J | Tile/carpet/windows | H | 8 | 10 | 12 | $6,000 |
K | Inspection | J | 0.5 | 1 | 1.5 | 0 |
L | Final detail work/cleanup | I, K | 20 | 25 | 60 | $4,500 |