Question: 1. Develop a network drawing for Towns Construction and determine the critical path. How long is the project expected to take? 2. What is the

1. Develop a network drawing for Towns Construction and determine the critical path. How long is the project expected to take?

2. What is the probabilityof finishing in 270 days?

Minnesota State University Project Data

Activity

Description

Predecessor(s)

Optimistic

Likely

Pessimistic

Cost/Day

A

Bonding, insurance, tax structuring

21

24

45

$1,500

B

Foundation, concrete footings for boxes

A

20

60

70

$3,500

C

Upgrading skybox stadium seating

A

50

60

100

$4,000

D

Upgrading walkways, stairwells, elevators

C

36

50

100

$1,900

E

Interior wiring, lathes

B

35

40

45

$9,500

F

Inspection approvals

E

1

1.5

2

0

G

Plumbing

D, F

22

26

36

$2,500

H

Painting

G

15

25

35

$2,000

I

Hardware/AC/metal workings

H

20

25

60

$2,000

J

Tile/carpet/windows

H

8

10

12

$6,000

K

Inspection

J

0.5

1

1.5

0

L

Final detail work/cleanup

I, K

20

25

60

$4,500

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!