Question: 1 . Develop an estimated duration for each activity. 2 . Using a project start time of 0 ( or May 1 5 ) and

1. Develop an estimated duration for each activity.
2. Using a project start time of 0(or May 15) and a required project
completion time of 180 days (or November 15), calculate the ES, EF, LS,
and LF times and TS for each activity. If your calculations result in a
project schedule with negative TS, revise the project scope, activity
estimated durations, and/or sequence or dependent relationships among
activities to arrive at an acceptable baseline schedule for completing the
project within 180 days (or by November 15). Describe the revisions
you made.
3. Determine the critical path, and identify the activities that make up the critical
path.
4. Produce a bar chart

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!