Question: 1- Develop AON/AOA for given activity charts (10 marks). JImmediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D

1- Develop AON/AOA for given activity charts (10

1- Develop AON/AOA for given activity charts (10 marks). JImmediate Estimated Activity Predecessor Completion Time A None 90 B A 15 C B 5 D G 20 E 21 F A 25 G CF 14 H 28 | A 30 D,1 45 DA5D Immediate Predecessors Activity A 19 Description Build internal components Modify roof and floor Construct collection stack 07 B 22 D Pour concrete and install frame 04 E 21 A A, B B, C D, E D, F, G F Build high-temperature burner Install pollution control system Install air pollution device Inspect and test 11 07 G H 05