Question: 1. Draw a box Project Network and Determine the Critical Path 2. Determine the best activity to crash by adding more labor to complete the
1. Draw a box Project Network and Determine the Critical Path
2. Determine the best activity to crash by adding more labor to complete the website in 15 days. (Show complete new project network BOX diagram.)
3. How many days can they delay information gathering until it lengthens the overall completion time for the website?

Activity Description Immediate Time (Days) Predecessor Information A 2 Gathering B Planning 3 C Design B 2 Content Writing D 3 and A.C Assembly E Coding C,D 6 Website F E 3 Testing Website G E 2 Review H Launch F,G 2