Question: 1. Draw a decision table with conditions 1,2 and 3 and actions a, b and c. How many rules are there in this table? Specifically,
1. Draw a decision table with conditions 1,2 and 3 and actions a, b and c. How many rules are there in this table? Specifically, if condition 1 is false, no actions are taken. If condition 1 is true and condition 2 is false and condition 3 is false action a is taken. If condition 1 is true, condition 2 is false and condition 3 true then actions a and b are taken. If cond 1 is true, cond 2 is true, cond 3 is false, actions a, b and c are taken. Otherwise no action is taken. 2. List five tasks that you need do before closing on a house. Draw a Gannt chart to illustrate a hypothetical timeline. What is meant by the critical path? Does your project have a critical path. note: please answer these 2 questions and draw them asked . Thank You