Question: 1. Draw a project network from the following information. (create and insert image) What activity(s) is a burst activity? What activity(s) is a merge activity?

1. Draw a project network from the following information. (create and insert image)

What activity(s) is a burst activity?

What activity(s) is a merge activity?

1. Draw a project network from the following

3. What is the difference between avoiding a risk and accepting a risk?

4. What is the difference between mitigating a risk and contingency planning?

ID Description Predecessor A A Survey site None B A Excavate site Install power lines B D Install drainage B E Pour foundation CD