Question: 1 ) Draw an Activity - on - Arrow Diagram ( use proper tool ) ii ) identifly project duration iii ) Slack for each

1)Draw an Activity-on -Arrow Diagram (use proper tool)
ii)identifly project duration
iii)Slack for each activity
iv) project criticla path for the following.
do step by step show the work
Activity name predecessor(s) Duration(weeks)
A none 20
B NONE 10
C NONE 10
D A,B 40
E C 10
F C,D 20
G E,F 10