Question: 1. Draw an AOA network for the project data shown below. a. Include in the diagram the ES, EF, LS, LF, TS for each activity

1. Draw an AOA network for the project data shown below.

a. Include in the diagram the ES, EF, LS, LF, TS for each activity and EET, LET for each event using the format shown below the table.

b. Highlight the critical path in the diagram.

c. Make a table that shows, for each task, total slack, free slack, interfering slack and independent slack. 1. Draw an AOA network for the project data shown

Activity Duration (weeks) 5 Predecessor (FTS, LAG=0) B 7 C 4 . D 5 B E 14 D F 10 D G 8 C H 7 G,F 1 3 F Legend ID TS EF EET LET ES LS LF Task Total Slack Free Slack Interfering Slack Independent Slack A B D E F G H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!