Question: 1) Draw the activity network for the following project using AON, and calculate the ES, EF, LS, LF times, then calculate the slack time for
1) Draw the activity network for the following project using AON, and calculate the ES, EF, LS, LF times, then calculate the slack time for each activity and determine the critical path:
| Activity | Activity Time (Normal) | Immediate Predecessors | Normal Cost | Crash Cost | Crash Time |
| A | 2 | - | $30,000 | $32,000 | 1 |
| B | 3 | A | $25,000 | $29,000 | 1 |
| C | 3 | A,B | $27,000 | $30,000 | 1 |
| D | 4 | B | $48,000 | $50,000 | 2 |
| E | 2 | C,D | $56,000 | $60,000 | 1 |
| F | 3 | E | $27,000 | $32,000 | 2 |
| G | 5 | E,F | $40,000 | $47,000 | 3 |
| H | 3 | F,G | $15,000 | $18,000 | 1 |
2) Calculate the crash cost per week for activity B and E then determine the new project timeline and the new critical path.