Question: 1) Draw the activity network for the following project using AON, and calculate the ES, EF, LS, LF times, then calculate the slack time for

1) Draw the activity network for the following project using AON, and calculate the ES, EF, LS, LF times, then calculate the slack time for each activity and determine the critical path:

Activity

Activity Time (Normal)

Immediate Predecessors

Normal Cost

Crash Cost

Crash Time

A

2

-

$30,000

$32,000

1

B

3

A

$25,000

$29,000

1

C

3

A,B

$27,000

$30,000

1

D

4

B

$48,000

$50,000

2

E

2

C,D

$56,000

$60,000

1

F

3

E

$27,000

$32,000

2

G

5

E,F

$40,000

$47,000

3

H

3

F,G

$15,000

$18,000

1

2) Calculate the crash cost per week for activity B and E then determine the new project timeline and the new critical path.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!