Question: 1. Draw the Activity-on-Node network diagram for the following table and work out the Early Start, Early Finish, Late Start, Late Finish, Free Slack and

1. Draw the Activity-on-Node network diagram for

1. Draw the Activity-on-Node network diagram for the following table and work out the Early Start, Early Finish, Late Start, Late Finish, Free Slack and Total Slack for all activities. Hand-drawn diagrams are acceptable, as long as it is clear. 2. Answer these 2 questions specifically:- a. How many days does it take to finish this project? b. Which tasks are on the critical path?4 tt Activity Duration (days) Preceding Activities A le 2e 3e 42 D- E Fe Ae A. Be Be D, E CE D G Fe F,H 64 Ge 62 2e le Je :3