Question: 1. The table below shows the activities, immediate predecessors, and the time estimates for these activities of a consulting project. a) Draw the network diagram

1. The table below shows the activities,
1. The table below shows the activities, immediate predecessors, and the time estimates for these activities of a consulting project. a) Draw the network diagram for this project ( 2 points) b) Indicate the Early Start, Early Finish, Late Start, and Late Finish Times for each of the activities on the network. ( 6 points) c) Identify the critical path and what is expected duration of the project? ( 2 points) d) Compute the slacks for each activity. (3 points)