Question: 1. Draw the AOA chart 2. There should be paths. 3. Critical length = days. 4. There should be non-critical activities. 5. There should be

1. Draw the AOA chart
2. There should be paths.
3. Critical length = days.
4. There should be non-critical activities.
5. There should be _____ dummy arc(s) in the AOA network.
Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of AOA while setting up AOA. Activity Immediate Predecessor(s) Time Duration (days) A None 5 B None 6 None 3 D A 5 E A,B 4 F C 7 G DE 6 H DE 9 1 HC 6Step by Step Solution