Question: Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of

Given the following table, construct an AOA

Given the following table, construct an AOA network and answer the following three questions. Note: You need to completely comply with the six rules of AOA while setting up AOA. Activity Duration (Days) Immediate Predecessor(s) A 6 None B 9 None 8 A,B D 7 A,B E 10 F 12 CE (1) There should be (2) Critical length = (3) There should be (4) There should be _paths. _days. _non-critical activities. dummy arc(s) in the AOA network