Question: 1. Draw the AOA chart. (sketch it on paper. Do the FP and BP calculations then write your name and submit) 2. In the response

1. Draw the AOA chart. (sketch it on paper. Do
1. Draw the AOA chart. (sketch it on paper. Do the FP and BP calculations then write your name and submit) 2. In the response template given at the end of the question, please fill the table (the 4 times and 4 types of floats) for all the activities. 3. What's (are) the critical path(s)? 4. How many dummies are in your AOA? Why did you use each dummy? Activity Predecessor Duration A 13 B 19 C 5 D B 11 E IC 16 F D C 17 G IC 14 H A 15 E,G 9 U F 8