Question: 1 Draw the AOA network for the House Construction Problem stated on Slide 5. node in the resulting AOA network. resulting AOA network. 2 Calculate
1 Draw the AOA network for the House Construction Problem stated on Slide 5. node in the resulting AOA network. resulting AOA network. 2 Calculate the Early Event Time and Late Event Time for every 3 Determine Total Float and Free Float for every activity (arc) in the 4 Determine a Critical path in the resulting AOA network. Task Label Task Duration Prerequisite (weeks) Tasks Masonry Carpentry for roof Roof Pipe and Electrical Installations Front of House WindowS Garden Ceiling Painting Moving In 8 2 D, C D, C D, C E, G, I