Question: 1 . Draw the network diagram using the information in the table. Identify the critical path ( s ) and how many days the critical
Draw the network diagram using the information in the table. Identify the critical paths and how many days the critical paths is Activity A B C D E F G H Days Predecessor A A B B C F D E G