Question: 1. Draw the PERT network diagram for a project below:2. Identify the critical path.3. Calculate the slack for each activity. Duration (weeks) Activity Immediate Optimistic

1. Draw the PERT network diagram for a project below:2. Identify the critical path.3. Calculate the slack for each activity.

1. Draw the PERT network diagram for a project below:2. Identify the

Duration (weeks) Activity Immediate Optimistic Most Likely Pessimistic Predecessor(s) (a) (m) (b) A None 7 16 28 B A 4 19 25 C A 10 16 37 D B 7 13 37 E B,C 13 19 33 F B 19 22 33 G DE 4 7 19 H F,G 13 19 49 | B,C 1 3 25 37 J |.H 7 13 19

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!