Question: 1. Draw the PERT network diagram for a project below:2. Identify the critical path.3. Calculate the slack for each activity. Duration (weeks) Activity Immediate Optimistic
1. Draw the PERT network diagram for a project below:2. Identify the critical path.3. Calculate the slack for each activity.

Duration (weeks) Activity Immediate Optimistic Most Likely Pessimistic Predecessor(s) (a) (m) (b) A None 7 16 28 B A 4 19 25 C A 10 16 37 D B 7 13 37 E B,C 13 19 33 F B 19 22 33 G DE 4 7 19 H F,G 13 19 49 | B,C 1 3 25 37 J |.H 7 13 19