Question: 1. Draw the project Network, for the example below, using the Arrow Diagram Method (ADM). 2. Calculate all possible paths to completion. (show workings) 3.
1. Draw the project Network, for the example below, using the Arrow Diagram Method (ADM).
2. Calculate all possible paths to completion. (show workings)
3. Identify the Critical Path.
4. You may provide your answer in a word document and attach it or send it separately.
| Software Development Project | |||
| Activity | Activity Description | Immediate Predecessors | Duration in Weeks |
| A | Define Software Project Objectives | none | 3 |
| B | Inventory new and old software features | none | 5 |
| C | Assemble team and allocate work | A,B | 2 |
| D | Design and develop code from and old database | C | 6 |
| E | Design and develop code for PC network | C | 5 |
| F | Test and debug PC network code | E | 3 |
| G | Design and develop code for off-site sales force | C | 4 |
| H | New complete test and debug | D,G,F | 3 |
| I | Train operators | D,F | 4 |
| J | Train outside sales force | H | 2 |
| K | Beta test of new system | I,J | 2 |