Question: 1. Using the below example, draw the network for the project using Arrow Diagram Method (ADM). 2. Calculate all the paths from start to the
1. Using the below example, draw the network for the project using Arrow Diagram Method (ADM).
2. Calculate all the paths from start to the completion of the project. (Show workings).
3. Identify the Critical Path.
| Software Development Project | |||
| Activity | Activity Description | Immediate Predecessors | Duration in Weeks |
| A | Define Software Project Objectives | none | 3 |
| B | Inventory new and old software features | none | 5 |
| C | Assemble team and allocate work | A,B | 2 |
| D | Design and develop code from and old database | C | 6 |
| E | Design and develop code for PC network | C | 5 |
| F | Test and debug PC network code | E | 3 |
| G | Design and develop code for off-site sales force | C | 4 |
| H | New complete test and debug | D,G,F | 3 |
| I | Train operators | D,F | 4 |
| J | Train outside sales force | H | 2 |
| K | Beta test of new system | I,J | 2 |