Question: 1. Find all expected activity times/durations ( TEs ) and variances. 2. Based on the computed TEs, draw an AON (Activity On Node) network diagram

1. Find all expected activity times/durations (TEs) and variances.
2. Based on the computed TEs, draw an AON (Activity On Node) network diagram representing all project activities, making sure to label activities and their durations.
3. Find the total slack for each activity.
\begin{tabular}{|c|c|c|c|c|} \hline Activity & Predecessors & \begin{tabular}{l} Optimistic \\ Duration \end{tabular} & \begin{tabular}{l} Most likely \\ Duration \end{tabular} & \begin{tabular}{l} Pessimistic \\ Duration \end{tabular} \\ \hline A & - & 7 & 10 & 19 \\ \hline B & - & 6 & 10 & 14 \\ \hline C & - & 6 & 11 & 22 \\ \hline D & A, B & 5 & 10 & 21 \\ \hline E & A & 7 & 15 & 17 \\ \hline F & C & 5 & 7 & 15 \\ \hline G & B, C & 8 & 9 & 16 \\ \hline H & D, E & 4 & 6 & 8 \\ \hline I & E, F & 6 & 7 & 14 \\ \hline J & F, G & 8 & 9 & 10 \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts