Question: 1) Following a chase strategy, how many workers would be needed in the month of March given that forecasted demand in March is 3,784 units,

1) Following a chase strategy, how many workers would be needed in the month of March given that forecasted demand in March is 3,784 units, there are 22 working days, and worker productivity is 4 units per day?

2) Following a chase strategy, how many workers would be needed in the month of March given that forecasted demand in March is 3,300 units, there are 22 working days, and worker productivity is 3 units per day?