Question: 1. From the list below, select those document that you will not be tracking as you go through the executing processes of the project. (Select
1.
From the list below, select those document that you will not be tracking as you go through the executing processes of the project. (Select the two best answers)
| A. | Risk register | |
| B. | Communications plan | |
| C. | Issues log | |
| D. | RFP | |
| E. | Change management form | |
| F. | Quality management metrics | |
| G. | Project schedule | |
| H. | Material safety data sheets (MSDS) | |
| I. | WBS | |
| J. | Budget | |
| K. | Resource requirements | |
| L. | Scope statement |
2.
Zeke Powers is a PM who works for a state government agency. He is currently heading up a project that involves the creation of a Human Services system to track such programs as foster care, and food stamps. The system must interact with various counties, and must remain in compliance with federal regulations so as to guarantee the current stream of funding dollars that allow the systems to stay in operation. With which regulatory environments will Zeke be concerned? (select the best answers)
| A. | Local | |
| B. | County | |
| C. | State | |
| D. | Federal | |
| E. | ISO | |
| F. | Law Enforcement |
3.
Many software developers like to pick their own working hours. It's not uncommon for a skilled developer to start working at midnight and work right through the night. Other groups of people often do the same thing--for example, road workers often have to work through the night when normally busy roads are not heavily traveled. What kind of problems does this pose for a PM? (Select the best answers)
| A. | Scheduling | |
| B. | Quality assurance | |
| C. | Time keeping | |
| D. | Task assignment | |
| E. | All of the above |