Question: 1.) Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 22, and 28 days respectively, compute the PERT expected activity time for
1.)
Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 22, and 28 days respectively, compute the PERT expected activity time for this activity.
| 7 | ||
| 22 | ||
| 20 | ||
| none of these | ||
| 18 |
2.)
We can find LS and LF using
| the ES and EF times | ||
| a backward pass through the network | ||
| backward and forward passes through the network | ||
| a forward pass through the network |
3.) Which of the following are major characteristics of projects? Choose all that apply.
| Has a defined life span with a beginning and an end | ||
| Requires all project activities to be completed by the same team | ||
| Has specific performance, time, and cost requirements | ||
| Has an established objective |