Question: A Moving to another question will save this response Question 62 of 75 LAVE ANSWER Question 62 1 points Given an activity's optimistic, most likely,
A Moving to another question will save this response Question 62 of 75 LAVE ANSWER Question 62 1 points Given an activity's optimistic, most likely, and pessimistic time estimates of 4, 12, and 18 days respectively, compute the PERT variance for this activity. O a. 5.44 O b. 8.00 O. 2.33 Od. 64.00 Moving to another question will save this response.