Question: 1 - Given the following network: a ) Find the earliest time the project will be completed. b ) Find the critical path.. c )

1- Given the following network:
a) Find the earliest time the project will be completed.
b) Find the critical path..
c) If activity I is delayed by 5 days, find the completion time of the entire project.
Activity t G
A 10
B 8 A
C 13 E H
D 8 C
E 7 D
F 12
G 13 B F I
H 5
I 10
==========================================
2 A food processor company uses approximately 10 glass jars a day for its fruit juice
product. Weekly holding cost is $0.20 per jar, and ordering cost is $40 per order.
a. Find optimal order quantity?
b. What penalty is the company incurring if they currently order Q=300?
c. If ROP=40, find LT..
d. Find number of orders per year.
============================================
3- ABC textile mills produces a special cloth. The demand for this cloth is 10 yards per day. The production
setup (ordering) cost is $100 per order and holding cost is $.20 per week. If production rate is 600 yards per
month, find;
a) Compute the optimal order quantity
b) Compute the production run time.
c) Find maximum inventory level.
d) Find the total cost
e) If SS=25, find TC.
========================================
4- Given the following product structure (BOM) and inventory status. Determine the quantity and timing of each
component that must be produced. Planned order for component A is 50 units in period 10.
Item OH(1)
A (LT=1)
A 0
B 30
D(LT=4) F(LT=3) C(LT=2) C 50
3 units 2 units 4 units D 40
E 100
F 50
B(LT=3) F(LT=3) B(LT=3) E(LT=5) D(LT=4)
4 units 1 unit 1 unit 3 unit 2 units

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!