Question: 1. Here are the two cash flow forecasts for two mutually exclusive projects.Find out each projects discounted payback, NPV, IRR, and MIRR at a cost
1.Here are the two cash flow forecasts for two mutually exclusive projects.Find out each projects discounted payback, NPV, IRR, and MIRR at a cost of capital of 8.25%.What is the projects crossover rate?Graph the NPV profiles for the projects.At what interest rates will you prefer project B to A?
TimeProject AProject B
0(8500)(9500)
136003900
224002900
328502900
452005550
2. Machines J and K have the following investment and operating costs:
Year0123
J1100012001300
K13000120013001400
Which machine is a better buy at a WACC of 10.5%?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
