Question: 1. Historical data indicates that the time required to complete a particular type of project follows a normal distribution with a mean completion time of
1. Historical data indicates that the time required to complete a particular type of project
follows a normal distribution with a mean completion time of 45 weeks and standard
deviation of 3 weeks.
a. What is the probability of completing the project in no more than 41 weeks?
b. What is the probability of completing the project in no less than 48 weeks?
2. Students enrolled in a particular course are preparing for an exam that will consist
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts