Question: 1. How many paths are there through this network? 1 2 3 4 2. How many critical paths are there? 0 1 2 3 3.

1. How many paths are there through this network?
1
2
3
4
2. How many critical paths are there?
0
1
2
3
3. Which activities have slack?
BC
CD
BE
CE
4.What is the slack for activity B?
0
1
2
3
5. What is the expected duration of this project?
13
14
15
16
Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created. Consider the following data for questions 1 through 5: Activity Duration Description Preceding Activity(ies) (days) A 2 Create script for advertisement B 2 Book technical crew A 5 Book actors A D Create props and costumes B,C E 3 Book location C F 5 Filming and editing DEStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts