Question: 1. How many paths are there through this network? 1 2 3 4 2. How many critical paths are there? 0 1 2 3 3.

1. How many paths are there through this network?

1. How many paths are there through this network?

1

2

3

4

2. How many critical paths are there?

0

1

2

3

3. Which activities have slack?

BC

CD

BE

CE

4.What is the slack for activity B?

0

1

2

3

5. What is the expected duration of this project?

13

14

15

16

Below are the project steps for the creation of a television advertisement for Foolio, which is a new energy drink that the musician Coolio has created. Consider the following data for questions 1 through 5: Activity Duration Description Preceding Activity(ies) (days) A 2 Create script for advertisement B 2 Book technical crew A 5 Book actors A D Create props and costumes B,C E 3 Book location C F 5 Filming and editing DE

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!