Question: 1) How many paths exist for the project to install a new server at the Northland Pines High School? 2) What is the critical path

1) How many paths exist for the project to

1) How many paths exist for the project to install a new server at the Northland Pines High School?

2) What is the critical path for the project to install a new server at the Northland Pines High School?

Activity Activity Time (days) Immediate Predecessor(s) Task A 2 Task B | 4 4 Task C 1 1 Task D 2 Task E 6 Task F 8 8 B, C Task G3 D, E Task H 5 Task. 4 Task J 5 G, H