Question: 1) How many paths exist for the project to install a new server at the Northland Pines High School? 2) What is the critical path

1) How many paths exist for the project to install a new server at the Northland Pines High School?
2) What is the critical path for the project to install a new server at the Northland Pines High School?
Activity Activity Time (days) Immediate Predecessor(s) Task A 2 Task B | 4 4 Task C 1 1 Task D 2 Task E 6 Task F 8 8 B, C Task G3 D, E Task H 5 Task. 4 Task J 5 G, H
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts