Question: 1) How would you create, a left justified schedule for the image attached. 2) Assuming you have five people available (with similar skills), level the
1) How would you create, a left justified schedule for the image attached.
2) Assuming you have five people available (with similar skills), level the schedule so it is consistent with resource availabilities. What is the new project duration?
3)or this project network, identify the critical sequence. (Frame your answer as Activity Node X to Activity Node Y to Activity Node Z, etc.)

\f
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts