Question: 1.) If everything goes wrong, ________ represents the time to complete the activity. least likely completion time optimistic time pessimistic time most likely time 2.)
1.)
If everything goes wrong, ________ represents the time to complete the activity.
| least likely completion time | ||
| optimistic time | ||
| pessimistic time | ||
| most likely time |
2.)
The primary difference between PERT and CPM is that
| PET has three time estimates | ||
| CPM has three time estimates | ||
| PERT uses one time estimate | ||
| with CPM, it is assumed that all activities can be performed at the same time. |
3.)