Question: 1. In Microsoft Project, the predecessors assigned to tasks will define the schedule because _________________. A. They link tasks together to establish relationships between the

1. In Microsoft Project, the predecessors assigned to tasks will define the schedule because _________________.

A.

They link tasks together to establish relationships between the start and/or completion of tasks.

B.

They identify potential risks with development activities

C.

They determine the timeline

D.

They define the skills required for specific tasks

2. During implementation, if new requirements are added to the project after the system design is finalized, the project team must focus on controlling the potential for _________.

A.

Scope creep

B.

Insufficient documentation

C.

Entitlements

D.

Risk creation

3. Which of the following is not an origin of an IT application change request, as discussed in lecture?

A.

Requested user enhancements to the application

B.

Changes to underlying software or network infrastructure

C.

Operational reports of problems

D.

Off-the-shelf competition advancements in the marketplace

4. identify the person in the list below that is not a high-profile usability expert?

A.

Jesse James Garrett

B.

Steve Krug

C.

Jakob Nielsen

D.

James Patterson

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!