Question: 1. In Microsoft Project, the predecessors assigned to tasks will define the schedule because _________________. A. They link tasks together to establish relationships between the
1. In Microsoft Project, the predecessors assigned to tasks will define the schedule because _________________.
| A. | They link tasks together to establish relationships between the start and/or completion of tasks. | |
| B. | They identify potential risks with development activities | |
| C. | They determine the timeline | |
| D. | They define the skills required for specific tasks |
2. During implementation, if new requirements are added to the project after the system design is finalized, the project team must focus on controlling the potential for _________.
| A. | Scope creep | |
| B. | Insufficient documentation | |
| C. | Entitlements | |
| D. | Risk creation |
3. Which of the following is not an origin of an IT application change request, as discussed in lecture?
| A. | Requested user enhancements to the application | |
| B. | Changes to underlying software or network infrastructure | |
| C. | Operational reports of problems | |
| D. | Off-the-shelf competition advancements in the marketplace |
4. identify the person in the list below that is not a high-profile usability expert?
| A. | Jesse James Garrett | |
| B. | Steve Krug | |
| C. | Jakob Nielsen | |
| D. | James Patterson |