Question: 1. Mary is taking over an ongoing project as a Project Manager. The earlier project manager is no more with the organization. Mary wants to
1. Mary is taking over an ongoing project as a Project Manager. The earlier project manager is no more with the organization. Mary wants to understand why the project should be executed, the high-level project requirements and budget of the project. Which document should Mary refer to?
Group of answer choices
Project Statement of Work
Project Management Plan
Project Charter
Business case
2. Crashing the schedule means:
Group of answer choices
Running the project team on overtime
Making the project shorter by any economic means
Doing activities that were in sequence in parallel
Getting out of town before the project is in trouble
3. Decomposing the major deliverables into smaller, more manageable components to provide better control is called:
Group of answer choices
Scope definition
Scope baselining
Scope verification
Scope planning