Question: 1. Mary is taking over an ongoing project as project manager. The earlier project manager is no more with the organization. Mary want to understand
1. Mary is taking over an ongoing project as project manager. The earlier project manager is no more with the organization. Mary want to understand why project should be executed, project requirements and budget on bird eye view. Which document she should refer? A. Project management plan B. Project statement of work C. Business case D.Projectcharter
2. You are the project manager for a software project. You are in the process of establishing the policies, procedures and documentation for planning, developing, managing, executing and controlling the project schedule. You may use all of the following Tools & Techniques except: A. Expert judgment B. Meetings C. Decomposition D. Analyticaltechniques
Give Justification for both the questions