Question: 1. Please complete the Resource-constrained Scheduling including which activity will start first, second, third, etc. Before assigning resources, the project will take ________ time units

1. Please complete the Resource-constrained Scheduling including which activity will start first, second, third, etc.

1. Please complete the Resource-constrained

  1. Before assigning resources, the project will take ________ time units to complete.
  2. Before assigning resources, the total slack (SL) time for activity C is ________ time unit(s).
  3. Before assigning resources, the total slack (SL) time for activity D is ________ time unit(s).
  4. You will first assign forklift(s) to activity ________.
  5. The third activity that you will assign forklift(s) to is activity ________.
  6. The fifth activity that you will assign forklift(s) to is activity ________.
  7. After assigning resources, the total slack (new schedule) for activity C is ________ time unit(s).
  8. After assigning resources, the total slack (new schedule) for activity F is ________ time unit(s).
  9. After assigning resources, period 3-4 will be required ________ forklifts.
  10. After assigning resources, period 4-5 will be required ________ forklifts.
  11. After assigning resources, period 8-9 will be required ________ forklifts.
  12. After assigning resources, it will take ________ time units to complete this project.
Legend ES ID EF SL RES SL LSPUR LF Develop a resource-constrained schedule in the loading chart provided below. Use the parallel method and heuristics discussed in class. List the order in which you scheduled the activities of the project and re-compute your slack for each activity given your new schedule. After that, answer the questions. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 ID RES DURO A 32 B 3 2 C1 2 3 4 4 F13 G 5 2 Resource Scheduled Resource | Available 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 Legend ES ID EF SL RES SL LSPUR LF Develop a resource-constrained schedule in the loading chart provided below. Use the parallel method and heuristics discussed in class. List the order in which you scheduled the activities of the project and re-compute your slack for each activity given your new schedule. After that, answer the questions. 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 ID RES DURO A 32 B 3 2 C1 2 3 4 4 F13 G 5 2 Resource Scheduled Resource | Available 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!