Question: Please help me ASAP. 2. Before assigning resources, the total slack (SL) time for activity C is ________ time unit(s). 3. Before assigning resources, the
Please help me ASAP.

2. Before assigning resources, the total slack (SL) time for activity C is ________ time unit(s).
3. Before assigning resources, the total slack (SL) time for activity D is ________ time unit(s).
4. You will first assign forklift(s) to activity ________.
5. The third activity that you will assign forklift(s) to is activity ________.
6. The fifth activity that you will assign forklift(s) to is activity ________.
7. After assigning resources, the total slack (new schedule) for activity C is ________ time unit(s).
8. After assigning resources, the total slack (new schedule) for activity F is ________ time unit(s).
9. After assigning resources, period 3-4 will be required ________ forklifts.
10. After assigning resources, period 4-5 will be required ________ forklifts.
11. After assigning resources, period 8-9 will be required ________ forklifts.
12. After assigning resources, it will take ________ time units to complete the project.
13. After assigning resources, which activities of your new schedule are now critical?
14. Please complete the Resource-constrained Scheduling including which activity will start first, second, third, etc.
You have prepared the following schedule for a project in which the key resources is a tractor. There are four tractors available to the project. To complete the project, activities A, D and Frequire three tractors; activities B and C requires two tractors, activities E and G require four tractors 8 2 10 2 B6 020 246 10 G 12 OIA12 030 0 2 2 G E 10 040- 6 4 10 10 2 12 2 C4 2 22 426 Legend ES D EF SL RES SLStep by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts