Question: 1 point Here is a task layout. Only one person can assigned to a task (no work sharing). You have three people available. Skills are

1 point Here is a task layout. Only one person
1 point Here is a task layout. Only one person can assigned to a task (no work sharing). You have three people available. Skills are not important. The effort involved all fits into the planned durations. Which group of tasks form the critical (longest) path? * Task 1: 1 day Task 2: 2 days Task 3: 1 day Start -Task 4: 2 days * Task 5. 3 days Task 6: 2 days End Task 7: 1 day --Task 8 6 days - Task 9: 1 day Task 3 - Task 6 - Task 9 Task 1 - Task 2 - Task 3 Task 4 - Task 5 - Task 6 Task 7 - Task 8 - Task 9