Question: 1. Project Alouette Task Description Duration Days Predecessor(s) Relationship p 2 Start FS+3 Q 1 Start R 2 Start D 2 p FS+7 E 3
1. Project Alouette
|
Task Description | Duration Days | Predecessor(s) | Relationship |
| p | 2 | Start | FS+3 |
| Q | 1 | Start |
|
| R | 2 | Start |
|
| D | 2 | p | FS+7 |
| E | 3 | Q | FS |
| F | 8 | R | FS |
| G | 4 | Q, D | Q(FS+S), D(SS+2) |
| H | 2 | E | FF+20 |
| I | 8 | F,G,H | FS |
| END | - | I | FS |
Hints: you will have to develop a network diagram and using Day 0 to perform CPM 1. The project duration is
days 2. The critical path acto\ivity names between start and end are
. Each name is separate by a dash. 3. The ESD of activity H is day
4. The LSD of activity F is day
5. The LSD of activity G is day
6. The EFD of activity D is day
7. The management will allow for 34 days to complete the project, the project float is
8. Will the project complete in 32 days? The answer is