Question: 1. Project Alouette Task Description Duration Days Predecessor(s) Relationship p 2 Start FS+3 Q 1 Start R 2 Start D 2 p FS+7 E 3

1. Project Alouette

Task Description

Duration Days

Predecessor(s)

Relationship

p

2

Start

FS+3

Q

1

Start

R

2

Start

D

2

p

FS+7

E

3

Q

FS

F

8

R

FS

G

4

Q, D

Q(FS+S), D(SS+2)

H

2

E

FF+20

I

8

F,G,H

FS

END

-

I

FS

Hints: you will have to develop a network diagram and using Day 0 to perform CPM 1. The project duration is

days 2. The critical path acto\ivity names between start and end are

. Each name is separate by a dash. 3. The ESD of activity H is day

4. The LSD of activity F is day

5. The LSD of activity G is day

6. The EFD of activity D is day

7. The management will allow for 34 days to complete the project, the project float is

8. Will the project complete in 32 days? The answer is

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!